This example preserves complete alphabetic and numeric revision histories for two controlled BESS handover documents.

Document ID Document Type System Area Owner Revision Approval Status Issue Date Supersedes Revision Evidence Link Closeout Notes
HND-101 As-built single-line diagram Electrical Engineering lead Rev A Superseded 2026-05-14 - Controlled drawings / HND-101 / Rev A Replaced after final cable routing walkdown.
HND-101 As-built single-line diagram Electrical Engineering lead Rev B Approved 2026-07-15 Rev A Controlled drawings / HND-101 / Rev B Matches the energized site configuration.
HND-102 Protection settings file Grid interface Protection engineer Rev 0 Superseded 2026-06-03 - Protection records / HND-102 / Rev 0 Replaced after utility witness testing.
HND-102 Protection settings file Grid interface Protection engineer Rev 1 Released 2026-07-18 Rev 0 Protection records / HND-102 / Rev 1 Released settings match the relay upload record.