Handover Acceptance Passing Record

Use this completed record to exercise cross-register acceptance checks for closed work, an approved deferral, and a conditional handover decision.

Punch-List and Nonconformance Tracker

ID Severity Finding or Nonconformance System Area Owner Evidence Link Target Close Date Status Verification / Closeout Note
PL-001 Major PCS grounding label was missing during the final walkdown. PCS Electrical supervisor DMS/Closeout/PL-001-photo.pdf 2026-07-18 Closed QA/QC lead verified the replacement label against the as-built tag list.
PL-002 Minor Auxiliary cabinet label schedule requires a controlled revision. Auxiliary power Document control lead DMS/Punch/PL-002-record.pdf 2026-08-05 Deferred Interim field labels and the approved residual-risk record control the handover period.
PL-003 Minor Archive copy of the operator attendance sheet is pending. Operations Training coordinator DMS/Training/attendance-draft.pdf 2026-07-25 In progress Archive after document-control receipt.

Residual-Risk Register

ID Source Item ID Risk Description Affected System Interim Control Owner Approval Target Close Date Status Closeout Evidence
RR-001 PL-002 Controlled label schedule is not yet issued. PCS / auxiliary power Field labels remain installed and operators received the approved handover note. Electrical supervisor Commissioning manager accepted on 2026-07-19 2026-08-05 Accepted for deferred closeout DMS/Risk/RR-001-acceptance.pdf

Acceptance Decision

Acceptance ID Decision Residual-Risk IDs Approved By Approval Date Evidence Location
ACC-001 Conditionally accepted RR-001 Owner representative 2026-07-21 DMS/Acceptance/ACC-001-signoff.pdf