Use this owner map to clarify who owns evidence, documents, commissioning decisions, operations handover, and residual risk during closeout.
| Role | Owned Artifact | Review Cadence | Escalation Path |
|---|---|---|---|
| Commissioning manager | Closeout plan, energization prerequisites, final acceptance package | Weekly until handover | Project director |
| QA/QC lead | Inspection records, NCR closeout, punch-list status | Twice weekly during closeout | Commissioning manager |
| Document control | Handover index, supplier manuals, as-built records | Weekly document-health review | Project controls |
| Electrical lead | Protection settings, test sheets, electrical completion evidence | At each hold point | Engineering manager |
| Controls engineer | PCS/BMS settings, alarms, event logs, interface test records | At each software/configuration release | Electrical lead |
| Operations lead | O&M readiness, training records, spares, warranty contacts | Before final walkdown | Asset manager |
| Project controls | Open-action tracker, schedule risk, closeout metrics | Weekly governance review | Project director |