bess-qaqc-toolkit

Commissioning Evidence Matrix

Use this matrix to map uniquely identified BESS commissioning checks to controlled evidence records needed for project closeout and handover.

Check ID System Area Check or Test Evidence IDs Acceptance Reference Owner Status
CHK-001 Battery racks Visual inspection complete EVD-001 Approved ITP / supplier manual QA/QC Not started
CHK-002 Battery racks Torque verification complete EVD-002 Installation procedure Electrical supervisor Not started
CHK-003 BMS Rack/module communication verified EVD-003 BMS commissioning procedure Controls engineer Not started
CHK-004 BMS Alarm and trip mapping verified EVD-004 Approved cause-and-effect matrix Controls engineer Not started
CHK-005 PCS Pre-energization checks complete EVD-005 PCS commissioning procedure Electrical supervisor Not started
CHK-006 PCS Charge/discharge command test complete EVD-006 SAT procedure Commissioning engineer Not started
CHK-007 EMS/SCADA Remote command interface verified EVD-007 SCADA point list / EMS procedure Controls engineer Not started
CHK-008 Fire safety Emergency stop interface verified EVD-008 Fire safety interface procedure HSE / commissioning Not started
CHK-009 Metering Revenue/settlement meter checked EVD-009 Metering specification Grid interface owner Not started
CHK-010 Grid interface Protection settings verified EVD-010 Protection study / grid-code requirement Protection engineer Not started
CHK-011 Performance Capacity or functional performance test complete EVD-011 Performance test procedure Commissioning manager Not started
CHK-012 Handover Punch list closure verified EVD-012 Handover plan Project controls Not started

Evidence Register

Replace each example location with the controlled document-system path and update the revision and approval status as evidence moves through review.

Evidence ID Evidence Location Revision Approval Status
EVD-001 DMS/Commissioning/battery-rack-visual-inspection.pdf 0 Pending review
EVD-002 DMS/Commissioning/battery-rack-torque-record.pdf 0 Pending review
EVD-003 DMS/Commissioning/bms-device-list.pdf 0 Pending review
EVD-004 DMS/Commissioning/bms-alarm-trip-test.pdf 0 Pending review
EVD-005 DMS/Commissioning/pcs-pre-energization-records.zip 0 Pending review
EVD-006 DMS/Commissioning/pcs-command-test.csv 0 Pending review
EVD-007 DMS/Commissioning/scada-interface-test.zip 0 Pending review
EVD-008 DMS/Commissioning/emergency-stop-test.pdf 0 Pending review
EVD-009 DMS/Commissioning/metering-verification.pdf 0 Pending review
EVD-010 DMS/Commissioning/protection-settings-pack.zip 0 Pending review
EVD-011 DMS/Commissioning/performance-test-report.pdf 0 Pending review
EVD-012 DMS/Handover/punch-list-closeout.xlsx 0 Pending review

Evidence Quality Rules

Closeout Questions