FAT Readiness Checklist

Use this checklist before factory acceptance testing for a battery energy storage system package.

Document Readiness

Item Evidence Required Status
Approved FAT procedure Controlled document with revision, acceptance criteria, and witness points Not started
Single-line diagram Approved drawing matching tested configuration Not started
Battery rack layout Rack/module/string configuration and serial-number mapping Not started
BMS architecture Communication topology, interface list, and firmware versions Not started
PCS datasheet Rated power, voltage window, protections, and compliance references Not started
Calibration records Valid certificates for test instruments Not started

Test Readiness

Item Evidence Required Status
Safety briefing complete Attendance record and test area risk review Not started
Test equipment available Equipment list with calibration validity Not started
Witness points agreed Client, supplier, and EPC responsibilities confirmed Not started
Pass/fail criteria defined Quantitative acceptance thresholds listed in FAT procedure Not started
NCR process available Nonconformance form and escalation owner identified Not started

Closeout

Item Evidence Required Status
FAT report drafted Results, deviations, and evidence attachments included Not started
Punch list created Owner, due date, severity, and closure evidence defined Not started
Shipment release decision Conditional or full release documented Not started