bess-qaqc-toolkit

Handover Document Index

Use this index to track the document package needed for BESS commissioning closeout, operations handover, and future audit review.

Document Index

Document ID Document Type System Area Owner Revision Approval Status Issue Date Supersedes Revision Evidence Link Closeout Notes
HND-001 As-built single-line diagram Electrical Engineering lead Rev C Approved 2026-07-18 - Drawing package / document control Confirm drawing revision matches energized configuration.
HND-002 Protection settings file Grid interface Protection engineer Rev 2 Pending approval 2026-07-19 - Relay upload record Require final utility acceptance before commercial operation.
HND-003 Battery rack torque records Battery racks Electrical supervisor Rev A Approved 2026-07-15 - Torque record folder Sample includes tool calibration certificate and rack serial range.
HND-004 Fire safety interface test record Fire safety HSE / commissioning Rev A Under review 2026-07-20 - Functional test report Confirm reset sequence and alarm visibility in SCADA evidence.
HND-005 Residual-risk register Project controls Commissioning manager Rev 0 Draft 2026-07-20 - Punch-list export Link any deferred items to approved owner and target close date.
                   
Type Examples
Drawings Single-line diagrams, layouts, cable schedules, network diagrams, as-built markups.
Procedures FAT, SAT, commissioning, energization, emergency response, isolation and lockout.
Certificates Meter calibration, instrument calibration, insulation test certificates, factory certificates.
Test records Functional tests, point-to-point checks, performance tests, protection tests, BMS/EMS logs.
Registers Punch list, nonconformance list, residual-risk log, spares list, training attendance.

Closeout Rules