SAT Readiness Checklist

Use this checklist before site acceptance testing for a BESS installation.

Site Readiness

Item Evidence Required Status
Installation complete Mechanical, electrical, and communication installation records Not started
Energization permit Approved site permit and switching plan Not started
Grounding verified Ground continuity and resistance test records Not started
Fire safety interface checked Fire alarm, suppression, and emergency stop interface records Not started
Network connectivity confirmed SCADA, EMS, BMS, PCS, and data gateway communication checks Not started

Commissioning Evidence

Item Evidence Required Status
Pre-commissioning tests complete Insulation, continuity, torque, and visual inspection results Not started
Firmware versions recorded BMS, PCS, EMS, and auxiliary controller versions Not started
Protection settings verified Approved settings file and field verification record Not started
Functional tests ready Charge/discharge, alarms, trips, and remote command cases Not started
Performance test plan approved Test cases, measurement method, and acceptance criteria Not started

Handover Readiness

Item Evidence Required Status
As-built package prepared Drawings, test records, manuals, certificates, and punch status Not started
Operator training complete Training agenda, attendance, and training material Not started
O&M documentation delivered Maintenance schedule, spare parts, emergency response instructions Not started