SAT Readiness Checklist
Use this checklist before site acceptance testing for a BESS installation.
Site Readiness
| Item |
Evidence Required |
Status |
| Installation complete |
Mechanical, electrical, and communication installation records |
Not started |
| Energization permit |
Approved site permit and switching plan |
Not started |
| Grounding verified |
Ground continuity and resistance test records |
Not started |
| Fire safety interface checked |
Fire alarm, suppression, and emergency stop interface records |
Not started |
| Network connectivity confirmed |
SCADA, EMS, BMS, PCS, and data gateway communication checks |
Not started |
Commissioning Evidence
| Item |
Evidence Required |
Status |
| Pre-commissioning tests complete |
Insulation, continuity, torque, and visual inspection results |
Not started |
| Firmware versions recorded |
BMS, PCS, EMS, and auxiliary controller versions |
Not started |
| Protection settings verified |
Approved settings file and field verification record |
Not started |
| Functional tests ready |
Charge/discharge, alarms, trips, and remote command cases |
Not started |
| Performance test plan approved |
Test cases, measurement method, and acceptance criteria |
Not started |
Handover Readiness
| Item |
Evidence Required |
Status |
| As-built package prepared |
Drawings, test records, manuals, certificates, and punch status |
Not started |
| Operator training complete |
Training agenda, attendance, and training material |
Not started |
| O&M documentation delivered |
Maintenance schedule, spare parts, emergency response instructions |
Not started |