Commissioning Hold-Point Checklist

Use this checklist to manage BESS commissioning gates where work should pause until required evidence, approvers, and release conditions are satisfied.

Hold Point Required Evidence Approver Release Condition Status Notes
Pre-energization readiness FAT/SAT records, insulation test results, grounding checks, and open punch-list export Commissioning manager / electrical lead No critical open items; required tests complete and reviewed Not started Cross-check the commissioning evidence matrix.
Battery rack energization Rack inspection records, BMS communication proof, torque evidence, and alarm status Battery lead / controls engineer All expected racks visible in BMS with no blocking alarms Not started Reference acceptance evidence wording guide.
PCS first power conversion PCS pre-checks, protection settings, command path, and emergency stop test Electrical lead / protection engineer PCS follows command at approved low-power setpoint Not started Capture command source and ramp behavior.
EMS/SCADA command release Point-to-point records, command hierarchy, alarm visibility, and operator access Controls lead / operations representative Operator can view state and command only approved functions Not started Confirm advisory vs direct-control commands.
Performance test start Approved test procedure, baseline conditions, metering readiness, and deviation list Commissioning manager / owner representative Test boundary conditions and acceptance criteria are agreed Not started Link residual-risk items if any test proceeds conditionally.
Handover release Handover document index, residual-risk register, punch-list closure, and closeout review Project manager / operations lead Operations accepts documents, residual risk, and known limitations Not started Use the closeout review checklist.

Reviewer Prompts