Use this guide to score handover document readiness before closeout review. Pair it with the handover document index and BESS closeout review checklist.
| Score | Readiness Level | Meaning | Closeout Action |
|---|---|---|---|
| 0 | Missing | Document is required but not available in the handover package. | Assign owner and target date before closeout can proceed. |
| 1 | Draft | Document exists but is uncontrolled, incomplete, or not ready for review. | Return to owner with required corrections. |
| 2 | Submitted | Document is in the package and ready for review but not approved. | Track reviewer, approval status, and comments. |
| 3 | Approved | Document has required technical approval but may not be accepted by all handover stakeholders. | Add approval record and confirm revision. |
| 4 | Accepted | Document is approved, indexed, linked, and accepted for handover. | Mark complete in the handover index. |
Add a readiness score column to the handover document index during weekly closeout review. Focus first on safety, protection, grid-interface, and commissioning-test records.